This week: part of the electrical installation has been completed in the booth and in the recording room, the parquet floor has been installed in the booth, the acoustic wall panels have been finally … more →
Casafont's Weblogcasafont wrote 1 year ago: This week: part of the electrical installation has been completed in the booth and in the recording … more →
casafont wrote 1 year ago: In the past two weeks part of the recording room’s acoustic walls has been assembled, the elec … more →
casafont wrote 1 year ago: Structurally, the recording studio Casafont is formed by three boxes, which correspond to: structure … more →
casafont wrote 1 year ago: This week the acoustic walls of the control room and the recording booth have been finished. The abs … more →
casafont wrote 1 year ago: This week the acoustic ceiling of the control room and the acoustic doors that were missing have bee … more →
casafont wrote 1 year ago: This week the acoustic ceiling of the recording room has been set up and that of the control room ha … more →
casafont wrote 1 year ago: This week the acoustic ceiling of the booth and part of the recording room has been finished. Moreov … more →