Backstage Construction Schedule February 28 - March 7, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for February 28 – March 7, 2015.  

Concrete pours for the ROOF… 349 more words

Construction Update

L Tower February 28 - March 7, 2015

8 The Esplanade – L Tower Saturday, February 28, 2015 – Saturday, March 7, 2015.

The Esplanade remains closed to car traffic eastbound from Yonge. City of Toronto crews closed it last Sunday because of a water main break. 160 more words

Construction Update

Construction, 2015

I was at Worcester State University the other day shooting an assignment for the school. While I was there I was asked to grab some photos of the new Wellness Center construction project in progress. 62 more words

Backstage Construction Schedule February 23 - 27, 2015

This is the REVISED construction schedule for 1 The Esplanade, Backstage condominium – for February 23 – 27, 2015.  

UPDATED: Concrete pours for the ROOF… 225 more words

Construction Update

L Tower February 23 - February 27, 2015

8 The Esplanade – L Tower Monday, February 23, 2015 – Friday, February 27, 2015.

New residents move in every week to the L Tower. Sidewalk work will resume once temperatures moderate sufficiently to permit it. 111 more words

Construction Update

Backstage Construction Schedule February 17 - 20, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for February 17 – 20, 2015.  

Note: Concrete pours for the 36… 240 more words

Construction Update

Backstage Saturday, February 14, 2015

This is the current construction schedule for 1 The Esplanade, Backstage condominium – for Saturday, February 14, 2015.  

Note: Extreme cold weather continues to cause delays and rescheduling of concrete pours and deliveries.  73 more words

Construction Update