Tags » Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of April 16th, 2018 and April 23rd, 2018

At Site A Excavation and dewatering work is Complete. Foundation footings have been poured. Slab on grade and foundation walls for Site A have begun and will be complete the week of 4/2. 162 more words

Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of April 2nd, 2018 and April 9th, 2018

At Site A Excavation and dewatering work is Complete. Foundation footings have been poured. Slab on grade and foundation walls for Site A have begun and will be complete the week of 4/2. 162 more words

Construction Updates

With the new entry walkway, we're making progress!

These three photos show the recently completed entrance, paved walk and hand-railing at the western end of the park — the first phase of work that started in December… 16 more words

News

DOMINO CONSTRUCTION UPDATE: Week of March 19th, 2018 and March 26th, 2018

At Site A Excavation and dewatering work is Complete. Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A have begun and will be complete in the next 2 weeks. 167 more words

Construction Updates

Texas Tech 2018... Day 7

Hola mi amigos, como estas?  Me llamo Gaeron y me gusto waffles.

Okay I am done with the Espanol, thought about writing this entire blog in Spanish but didn’t want to make anyone struggle with their translation. 1,929 more words

Community Ministry

DOMINO CONSTRUCTION UPDATE: Week of March 5th, 2018 and March 12th, 2018

At Site A Excavation and dewatering work is Complete. Some foundation footings have been poured and are continuing to be installed. Slab on grade and foundation walls for Site A have begun and will be complete in the next 2 weeks. 167 more words

Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of February 19th, 2018 and February 26th, 2018

At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete.Some foundation footings have been poured and are continuing to be installed. 194 more words

Construction Updates