Tags » Construction Updates

Construction Committee Meeting 2/15/2018 – Summary

On February 15th, we held our fourth Construction Committee meeting in the construction trailer at the site. In attendance were the Linden Neighborhood Association, the Wylie Court Condo Association, the general contractor, and the developer. 403 more words

Construction Updates

MOH & Rollins Family Trip - Day 1

From Mission of Hope….

We Made It!!!!  We flew into PAP, Haiti last night around 5:45 and began our journey.  We took an hour and a half school bus ride to Wahoo resort and saw our boat as we drove up…it was so very exciting!  832 more words

Team Ministry

Neighborhood Streetscape Improvements (Final Plan)

On January 24th 2018, Agave Ponce LLC, Dover Kohl & Partners, the City of Coral Gables and the neighbors met at the Police station Meeting Room to go over the final Proposed Streetscape Improvements based on the previous sessions and meetings. 95 more words

The Plaza Coral Gables

DOMINO CONSTRUCTION UPDATE: Week of February 5th, 2018 and February 12th, 2018

At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete.Some foundation footings have been poured and are continuing to be installed. 188 more words

Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of January 22nd, 2018 and January 29th, 2018

At Site A Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is complete and production piles along with tie back installation is complete. 207 more words

Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of January 8th, 2018 and January 15th, 2018

At Site A  Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is continuing daily and production piles along with tie back installation is complete. 200 more words

Construction Updates

DOMINO CONSTRUCTION UPDATE: Week of December 25th, 2017 and January 1st, 2018

At Site A  Excavation and dewatering work is ongoing and SOE and pile driving is complete. Excavation and trucking of soil is continuing daily and production piles along with tie back installation has begun. 187 more words

Construction Updates