Tags » Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of May 28, June 4, & June 11.

At Site A the ground floor and 2nd floor slab are complete. The 3rd floor concrete should be completed by 6/22. The Con-Ed vaults will be installed on Kent Ave this will reroute bike and pedestrian traffic for 3-4 weeks. 64 more words

Construction Updates

Building Update: Lab & Pharmacy

My dad’s buildings have withstood floods, earthquakes, & hurricanes! So I obviously wanted him to be the construction foreman for this medical addition!

Due to the… 351 more words

Construction Updates

DOMINO CONSTRUCTION UPDATE: Weeks of April 30, May 7 & May 14, 2018

At Site A Foundation work is complete and the foundation contractor has demobilized. Ground Floor Slab and foundation walls for Site A are complete. Underground plumbing and electric work is complete. 131 more words

Construction Updates

Episode 101 - News 5/9/18

Today’s news topics include:

  • Avenger’s Infinity War reaches 1 Billion faster than any movie in history
  • First look at Alien Swirling Saucers
  • Animatronic Wheezy is added to the end of Slinky Dog Dash…
  • 130 more words
Travel

DOMINO CONSTRUCTION UPDATE: Week of April 16th, 2018 and April 23rd, 2018

At Site A Foundation work is complete and the foundation contractor has demobilized. Slab on grade and foundation walls for Site A are complete. Underground plumbing and electric work is complete. 153 more words

Construction Updates

Wanted: Neighborhood Input for Landscaping

 

There are two main lift stations that will serve our neighborhood sewer system.  Lift Station 1 is on the north side of Tanglewood at Tuttle Ave.   81 more words

Neighborhood Committee

DOMINO CONSTRUCTION UPDATE: Week of April 2nd, 2018 and April 9th, 2018

At Site A Excavation and dewatering work is Complete. Foundation footings have been poured. Slab on grade and foundation walls for Site A have begun and will be complete the week of 4/2. 162 more words

Construction Updates